20171214 / Relocation in the new Datacenter (SING)

Tests on electrical system will occur from 14th to 19th of december (with full charge and discharge on UPS).

Full discharge, and fire tests, will occur on 18th of december.

Water cooling system is not yet at 100% capacity…

Hey! First day without problems!

More to come tomorrow.