20171215 / Relocation in the new Datacenter (SING)

Yoohou! Second day without problems!

Full discharge on UPS systems, with fire security tests, will occur on 18th of december (full power outage involved).

Water cooling system is announced, for sure, at 50% capacity (which is enough, for now).

Everything will be poweroff on monday, 18th of december, around 11h00.