20171222 / Relocation in the new datacenter (SING)

Everything goes strictly as planned, except:

- 10 days of elevator failure → 4 days delay.

- 2 days of elevator (another one) failure during the relocation of our offices → +2 days delay.

- snowfall 1 day → +1 day delay.

- flooding in our previous offices, we had to rush to empty them of all remaining stuff → +2 days delay.

WE ARE IN TESTING MODE. NO PRODUCTION. NO ACCESS.

New login/passwd will be send to everyone, as soon as we are ready. Not before. Please wait till PSMN is up and running. We will contact you.