newsfeed:20171222 [2017/12/22 08:14] – [20171222 / Relocation in the new datacenter (SING)] gilquin | newsfeed:20171222 [2020/08/25 15:58] (Version actuelle) – modification externe 127.0.0.1 | ||
---|---|---|---|
Ligne 3: | Ligne 3: | ||
Everything goes strictly as planned, except:\\ | Everything goes strictly as planned, except:\\ | ||
- | - 10 days of elevator failure -> 4 days delay.\\ | + | * 10 days of elevator failure -> 4 days delay.\\ |
- | - 2 days of elevator (another one) failure during the relocation of our offices -> +2 days delay.\\ | + | |
- | - snowfall | + | |
- | - flooding in our previous offices, we had to rush to empty them of all remaining stuff -> +2 days delay.\\ | + | |
**WE ARE IN TESTING MODE. NO PRODUCTION. NO ACCESS.** | **WE ARE IN TESTING MODE. NO PRODUCTION. NO ACCESS.** | ||
- | New login/ | + | New login/ |
Please wait till PSMN is up and running. We will contact you. | Please wait till PSMN is up and running. We will contact you. | ||