20171222 / Relocation in the new datacenter (SING)

Everything goes strictly as planned, except:

  • 10 days of elevator failure → 4 days delay.
  • 2 days of elevator (another one) failure during the relocation of our offices → +2 days delay.
  • snowfall/rain inside the building → +1 day delay.
  • flooding in our previous offices, we had to rush to empty them of all remaining stuff → +2 days delay.

WE ARE IN TESTING MODE. NO PRODUCTION. NO ACCESS.