====== 20171222 / Relocation in the new datacenter (SING) ====== | ====== 20171222 / Relocation in the new datacenter (SING) ====== | ||
- | Everything goes strictly as planned, except: | + | Everything goes strictly as planned, except:\\ |
- | - 10 days of elevator failure -> 4 days delay. | + | |
- | - 2 days of elevator (another one) failure during the relocation of our offices -> +2 days delay. | + | - 10 days of elevator failure -> 4 days delay.\\ |
- | - snowfall 1 day -> +1 day delay. | + | - 2 days of elevator (another one) failure during the relocation of our offices -> +2 days delay.\\ |
- | - flooding in our previous offices, we had to rush to empty them of all remaining stuff -> +2 days delay. | + | - snowfall 1 day -> +1 day delay.\\ |
+ | - flooding in our previous offices, we had to rush to empty them of all remaining stuff -> +2 days delay.\\ | ||
**WE ARE IN TESTING MODE. NO PRODUCTION. NO ACCESS.** | **WE ARE IN TESTING MODE. NO PRODUCTION. NO ACCESS.** |